AQW 30980/22-27 Written question to the Minister for Infrastructure
To ask the Minister for Infrastructure to detail any road repairs carried out on (i) Farmley Park; and (ii) Farmley Gardens, Newtownabbey, in the last 24 months.
Asked by Nuala McAllister MLA on 11 September 2025
- Answered
- Written
- After due date
- Tabled
- 11 September 2025
- Answer due by
- 26 September 2025
- Answered
- 30 September 202519 days after tabling
- Department
- Department for Infrastructure
- Priority question
- No
Answer
Defects within Farmley Park and Gardens, which have resulted in road repairs in the last 24 months, are detailed below:
| Farmley Park | Farmley Gardens |
| 9 carriageway defects (potholes) 8 repaired / 1 outstanding | 9 carriageway defects (potholes) 7 repaired / 2 outstanding |
| 2 footway defects (potholes) complete | 2 footway defects (potholes) 1 repaired / 1 outstanding |
| 3 road marking defects 2 repaired / 1 outstanding | 1 road marking defects 1 outstanding |